Maine House, protecting sand dunes, rejects plan to build offshore wind terminal on Sears Island

Portland Press Herald|Stephen Singer |April 10, 2024
MaineImpact on LandscapeOffshore Wind

The Maine House of Representatives voted Tuesday to protect sand dunes on Sears Island where the Mills administration has proposed to build an offshore wind terminal. In an 80-65 vote, the House rejected legislation that would have authorized the Department of Environmental Protection to grant a permit to build the terminal on an area of Sears Island that includes a coastal sand dune system. If the legislation fails, it is unclear how severely the decision would delay the buildout of a wind port in Maine, where turbines and other components would be assembled and then shipped to the Gulf of Maine. The project involves lengthy state and federal permitting processes after a site is selected.


It is unclear how severely the decision will delay the buildout of a wind port in Maine, which would create hundreds of high-paying jobs and advance the state's climate goals.

The Maine House of Representatives voted Tuesday to protect sand dunes on Sears Island where the Mills administration has proposed to build an offshore wind terminal.

In an 80-65 vote, the House rejected legislation that would have authorized the Department of Environmental Protection to grant a permit to build the terminal on an area of Sears Island that includes a coastal sand dune system.

If the legislation fails, it is unclear how severely the decision would delay the buildout of a wind port in Maine, where turbines and other components would be assembled and …

... more [truncated due to possible copyright]

It is unclear how severely the decision will delay the buildout of a wind port in Maine, which would create hundreds of high-paying jobs and advance the state's climate goals.

The Maine House of Representatives voted Tuesday to protect sand dunes on Sears Island where the Mills administration has proposed to build an offshore wind terminal.

In an 80-65 vote, the House rejected legislation that would have authorized the Department of Environmental Protection to grant a permit to build the terminal on an area of Sears Island that includes a coastal sand dune system.

If the legislation fails, it is unclear how severely the decision would delay the buildout of a wind port in Maine, where turbines and other components would be assembled and then shipped to the Gulf of Maine. The project involves lengthy state and federal permitting processes after a site is selected.

The legislation, which is narrowly crafted to reference the sand dunes, would allow the DEP to act only after all laws and agency rules also permit construction.

The sand dune area is about four-tenths of an acre, according to the bill, which now heads to the Senate.

Gov. Janet Mills announced in February her selection of Sears Island for Maine’s foray into wind power. She said it was not an easy decision, and it was opposed by environmentalists who favored nearby Mack Point.

Criticism quickly focused on the potential threat that construction would pose to the sand dunes. Maine Audubon says sand dunes and coastal beaches protect buildings and infrastructure from waves and flooding and provide habitat for migratory shore birds, and endangered and threatened species.

Ben Goodman, a spokesman for Mills, said the legislation affects a “small, manmade – not naturally occurring – sand dune system” on state Department of Transportation land on Sears Island that was created by the placement of a jetty.

Without the legislation or “commensurate language elsewhere,” Maine would lose a “once-in-a-generation opportunity” to create hundreds of well-paid jobs, generate clean energy and protect the environment against climate change and the health of Mainers, he said.

DUELING ENVIRONMENTAL CONCERNS

Several lawmakers said during the House debate that they were conflicted between voting to allow construction that could undermine the island’s environment and advancing Maine’s wind energy industry, which is essential to helping cut carbon-based energy.

Environmentalists say wind from the Gulf of Maine is among the strongest and most consistent available, and offshore wind is expected to generate about half the renewable energy needed by Maine by the end of the next decade.

Jack Shapiro, climate and clean energy director for the Natural Resources Council of Maine, said taking Sears Island out of the running for Maine’s wind port would be unfortunate and short-sighted. The necessary permits require the applicant to demonstrate that they have evaluated all of the alternatives.

“We think the stakes are too high for offshore wind and too high for the climate to do that without all the evidence in hand,” he said. 

He could not speak directly to the timeline, but said if the bill fails it will likely cause “significant delays” in what already is expected to be a multiyear process.He’s hopeful that it won’t get to that point. 

“We’re hopeful that we can move forward with both sites under consideration because we want to pick the best site for Maine that gives us the best chance to develop this resource and meet our climate goals in a timely manner,” Shapiro said, referring to Mack Point as the other site. 

SAND DUNE DILEMMA

Rep. Valli Geiger, D-Rockland, who described herself as an environmentalist, said she finds it difficult to “roll back our sand dune regulations because it’s in the way of development.”

Yet Geiger said the wind port is a rare opportunity to contribute to the fight against climate change and create well-paid manufacturing jobs.

“Ultimately, for me it’s the larger overarching issue of climate change that has led me to ‘yes,’ ” she said.

Rep. Mike Soboleski, R-Phillips, said “it’s hard to reconcile destroying part of the environment to save the environment” and questioned whether wind power will accomplish what advocates claim.

“I think we should hold off on this, see if they’re actually viable, if they do work, if they do make a difference, if they can help our environment, if they can save on electrical bills, which so far we haven’t seen that at all,” he said.

The 100-acre site on Sears Island was one of several considered in a more than two-year review by Maine officials. Portland, Eastport and Mack Point – which is also in Searsport – also were considered. State environmental officials said the Sears Island site would not require dredging, unlike at Mack Point.

The Sears Island site is on one-third of the island that the state Department of Transportation has reserved for development. The other two-thirds are in a permanent conservation easement held by the Maine Coast Heritage Trust.

The legislation establishes within DEP a $1 million Coastal Sand Dune Restoration and Protection Fund that the agency can use to pay up to 50% of eligible costs incurred in a project to restore, protect, conserve or “revegetate” a coastal sand dune system and up to 100% of eligible costs for projects relating to coastal sand dune systems.

Staff Writer Hannah LaClaire contributed to this report. 

RELATED HEADLINES
Mills administration taking next steps to advance Sears Island offshore wind project
State selects Sears Island as preferred site for Maine’s new offshore wind port
Critics call plan for Searsport offshore wind site ‘dangerous precedent,’ point to coastal impacts


Only subscribers are eligible to post comments. Please subscribe or login first for digital access. Here’s why.

Send questions/comments to the editors.

Norfolk Southern agrees to $600 million settlement in fiery Ohio derailment
Last-minute budget cut to Maine dairy subsidy riles farmers
FILED UNDER:
OFFSHORE WIND, SEARSPORT MAINE, TIMES RECORD NEWS
RELATED STORIES
BUSINESS
NASA satellite could help identify best places to grow oysters, scallops in Gulf of Maine
BUSINESS
Critics call plan for Searsport offshore wind site ‘dangerous precedent,’ point to coastal impacts
MAINE
Mills administration taking next steps to advance Sears Island offshore wind project
Oregon Offshore WindMAINE
Feds announce 2 million-acre site in Gulf of Maine for offshore floating wind project
Offshore Wind First PowerBUSINESS
The United States has its first large offshore wind farm, with more to come
LATEST ARTICLES
Measles-Explainer
NEWS
Measles cases in U.S. up in 2024. What’s driving the increase?
Biden Arab Americans
NATION / WORLD
Muslim leaders are ‘out of words’ as they tire of the White House outreach on war in Gaza
Disney-DeSantis
BUSINESS
Some Disney fans abused disability access to skip lines. Now rules are changing.
Instagram Nudity
BUSINESS
Instagram begins blurring nudity in messages to protect teens and fight sexual extortion

POLITICS
Governor, House speaker call on Senate president to reconvene budget committee
THE BUZZ
Get business headlines delivered to your inbox every Thursday at 10 a.m.
Enter your email
Enter your email
MOST READ STORIES
Update: Pedestrian in serious condition after being struck Wednesday night by SUV in Lewiston
Sebago Lake property owner to pay over $650,000 in shoreland zoning violations settlement
Mike Adams steps down after coaching Edward Little boys basketball for 23 years
Lewiston council changes rule after mayor criticized for not making timely appointments
Hearing to consider removing Sheriff Wainwright from office is scheduled for April 22
Lewiston Sun Journalfacebook twitter Instagram youtube linkedin
CONTACT US
Staff Directory
About the Sun Journal
About Maine Trust for Local News
Send a News Tip
Send a Letter to the Editor
Send a Press Release
Send an Announcement
Add an Event
Ask Sun Spots
SUBSCRIBERS
Manage Your Account
Log a Delivery Issue
Subscriber Resources
Subscriber Benefits
Access ePaper
Search Archives
Mobile Apps
FAQs
CONNECT WITH US
Email Newsletters
Facebook
Instagram
YouTube
ADVERTISE
Advertise with Us
Contact Advertising
Submit an Obituary
NETWORK
Work Here
Centralmaine.com
Pressherald.com
Timesrecord.com
Varsitymaine.com
Advertiser Democrat
Bethel Citizen
Franklin Journal
Livermore Falls Advertiser
Rangeley Highlander
Rumford Falls Times
Privacy Policy Cookie Policy Terms of Service Commenting Terms Public Notices Photo Store Merch Store Archives
© 2024 | All Rights Reserved | Lewiston Sun JournalSome areas of this page may shift around if you resize the browser window. Be sure to check heading and document order.


Source:https://www.sunjournal.com/20…

Share this post
Follow Us
RSS:XMLAtomJSON
Donate
Donate
Stay Updated

We respect your privacy and never share your contact information. | LEGAL NOTICES

Contact Us

WindAction.org
Lisa Linowes, Executive Director
phone: 603.838.6588

Email contact

General Copyright Statement: Most of the sourced material posted to WindAction.org is posted according to the Fair Use doctrine of copyright law for non-commercial news reporting, education and discussion purposes. Some articles we only show excerpts, and provide links to the original published material. Any article will be removed by request from copyright owner, please send takedown requests to: info@windaction.org

© 2024 INDUSTRIAL WIND ACTION GROUP CORP. ALL RIGHTS RESERVED
WEBSITE GENEROUSLY DONATED BY PARKERHILL TECHNOLOGY CORPORATION